Generate Job Measure Costs
Before we can report on the "Measure to date" progress for the job we need to generate Job Measure Costs. This takes a snapshot of the project and the current job transactional data. This data is held in a specific weekly reporting table, and the job cost data will not change for the week, unless the "generate job measure costs" function is rerun. It is important that this function is run right at the end of the week, after all data entry and Job Measure Accruals have taken place so that the reporting is as up to date and as accurate as possible.
- From the contract drop down list select the "Contract" that you wish to generate measure costs for.
- Select the week ending date for which to generate the snapshot, Upon opening this screen the week ending date will default to the week ending date of the current week.
- Click the Generate button to generate the snapshot.
(You can also preview the output of this by clicking in the Preview Output via Query check box.)