Job Work Centre Setup
Select the "Job Work Centres" button from the "Job Estimate Entry" screen.
On the "Job Work Centres Maintenance" screen, Set up the Work Centres you require for your contract.
- Select Job Code
- Select the Work Centre Code ( You can only use each Work Centre code once per job)
- Either use the default description for the Work Centre or type in your own, if you are using very generic Work Centres you will probably need to rename Work Centres every time.
- Enter a Start Date and End Date for these Work Centres if desired, this isn't required for Measured Outputs though. These are used in Project Cashflows (Not Covered as part of this Manual)
- Enter the Output unit for this Work Centre e.g. Days, Hours, Metres
- Enter the Output Budget for this Work Centre this is the quantity of Outputs to be delivered based on the Unit of Measure.
- Balance of Budget (This is covered in Contract Forecasting and is not required as part of this Manual)
The "Job Work Centre Output Budget Entry" can also be accessed from the menu.
This will allow entry of the Budgeted Output quantity only.