The first priority is a high level over-ride Mark Up%. It is a MU% with no Activity or Item selected. If used it becomes the markup% for all non labour transactions. It overrides all other Retail calculations.


If there is any conflict in priority where both Items and Activities are selected in the Price Code the Item takes precedence over the Activity.
Note: Where you have selected an Item or Activity as well as the high level over-ride the specific takes precedence over the over-ride.

  • No labels