There are costs of $20,000 in Job 8020. This is a sequence 1 allocation using a fixed type to each of the Profit Centre Jobs.

The Mastitis Profit Centre Job is then allocated to all of its SubJobs based on the current costs in each of those SubJobs.

 

The screens that follow already show the allocation as the Generate Cost Allocations has been run.
This shows the Cost Allocation Schedule printed after calculation.